Published on Australian Maritime Safety Authority (https://www.amsa.gov.au)



Operational updates—YM Efficiency

Stay tuned for regular updates on Operation Recovery—YM Efficiency

tyres underwater

Hundreds of tonnes of container waste processed 

Onshore crew at Port of Newcastle have finished the enormous task of processing 720 tonnes of waste recovered from waters off the Hunter Coast. 

The final six of 63 identified YM Efficiency containers recovered by the MV Pride were discharged on 8 May and processing was completed on 10 May. 

The containers holding furniture, chip packets and other foodstuffs, were opened and processed for safe disposal.

During a four-week period from 12 April when the first containers were discharged onshore, crew identified 440 tonnes of general solid waste for landfill.

In addition, 195 tonnes of metal, including empty containers were sent for scrap metal processing, 67 tonnes of tyres mustered for recycling and 18 tonnes of liquid waste collected for safe disposal.

Overall the operation took 34 days, including 7.5 days of weather delays and no additional marine pollution reported. 

We thank seafarers from both Australia and overseas who have completed this work away from their homes and families in this time of a global pandemic.

Packets of chips were among the contents of the final six containers.
Packets of chips were among the contents of the final six containers.
Packets of chips were among the contents of the final six containers.
Foodstuffs that could have harmed wildlife or washed ashore have been processed for safe disposal.
Container of furniture was unpacked for disposal.
Container of furniture was unpacked for disposal.

 

 

Show all / Hide all

8 May: Five-week coastal clean-up ends 

All 63 identified shipping containers lost overboard from the YM Efficiency in June 2018, have been recovered off the Hunter Coast.

Offshore construction vessel, MV Pride, which carried out the five-week operation, has returned to Port of Newcastle to discharge the final six containers onshore.

It brings an end to subsea operations to recover thousands of tonnes of waste and pollution that has mired Newcastle-Port Stephens coastal communities for almost two years.

The final six containers will be processed by waste crews for salvage, recycling or landfill.

We are thankful to the seafarers who have worked on this operation.

Crushed and damaged containers will be sent straight to a metal scrapping facility.
Crushed and damaged containers will be sent straight to a metal scrapping facility.
Crushed container delivered to shore
Final six recovered containers have been delivered to shore for processing.
7 May: Final days of retrieval operation

Crew on MV Pride have recovered 36 steel beams and their broken container, plus a container holding foodstuff and beverages. 

There are three remaining steel beams to be removed from the seabed, followed by a site survey.

To date, 59 containers have been retrieved and there are four yet to be recovered. 

Conditions are expected to improve, aiding the efforts to bring offshore operations to a close. 

Two containers originally holding 39 steel beams will be processed as scrap metal onshore.

recovered containers
Two containers originally holding 39 steel beams will be processed as scrap metal onshore.

 

6 May: Steel beams slow down recovery efforts 

Operations have resumed overnight to retrieve debris and the final six identified containers off the Hunter Coast. 

Crew recovered a hydraulic tank and motor, a corner section of a container and discovered two containers split open with a number of steel beams spilling out.  

Due to their weight, each beam was lifted separately by MV Pride’s heave compensating crane, which slowed overnight recovery operations. Both containers are yet to be recovered and the site cleared of debris.

Recovery of steel beams spilled out of containers
Recovery of steel beams spilled out of containers.
tank and pump
Machinery is prepared for retrieval at one of the final container recovery sites.

 

 

5 May: Recoveries set to resume 

Operational crew on MV Pride are planning to recommence work by this evening to recover the remaining six containers off the Hunter Coast. 

Bridge crew are monitoring conditions for changes, with high seas and wind gusts expected to ease off today. 

Robotic grab used to collect loose debris from the seabed
Robotic grab used to collect loose debris from the seabed

 

4 April: Recoveries paused during poor conditions

Salvage operations have been on hold since Friday due to high winds and rough seas.

Bridge crew aboard MV Pride are monitoring conditions for any changes and will resume container recoveries once weather improves off the Hunter Coast.

All discharged containers have been processed by waste crew at Port of Newcastle for salvage, recycling and landfill.

To date, 57 containers have been retrieved and the remaining six containers will be retrieved at the earliest opportunity.

sweeping container
Waste crew have completed onshore container processing until the next tranche is delivered.

 

1 May: Video opens the door on container waste

Waste crews at Port of Newcastle will continue processing tonnes of solid and liquid waste while subsea container recovery operations are on hold.

Retrieval of the final six containers from the Hunter Coast seabed are being paused while MV Pride awaits an improvement to the current high seas and rough conditions.

Onshore, 67 truckloads of general waste and recycling, metal scrap and tyre recycling have been processed and storage tanks for liquid and bunded waste have been pumped out twice for safe disposal.

Around 35 emptied containers have been metal scrapped and mobility scooter batteries will be transferred to a licensed hazardous waste facility.

Offshore operations are expected to resume next week or when weather conditions improve.

You can check out our amazing footage of subsea and vessel operations, and witness the opening of the first few containers onshore.

Rough weather has stalled offshore operations, while crews working onshore are still processing tonnes of waste.
Rough weather has stalled offshore operations, while crews working onshore are still processing tonnes of waste."

 

30 April: Waste processing continuing onshore 

Three damaged containers were retrieved off the Hunter Coast overnight before operations were halted due to rough conditions.

Containers holding a machinery test bed, toilet paper and nappy absorbent were stored on board MV Pride and crew carried out site surveys for loose debris.

At Port of Newcastle, waste processing of 11 containers is complete, including cleaning and disposal of discharged containers. There are three containers left to process ahead of site preparations for the next load of containers to be discharged ashore.

To date, 57 containers have been retrieved and there are six identified containers yet to be recovered.

High seas and increased wind speeds expected over the weekend will likely delay the recovery of the remaining containers until early next week.

Waste crew are processing another container of nappy absorbent
Waste crew are processing another container of nappy absorbent
Plastics will be sorted for recycling where possible
Plastics will be sorted for recycling where possible

 

29 April: 70-tonnes of furnishings recovered overnight

Crew aboard MV Pride retrieved two containers of toilet paper and a 70-tonne container of furnishing products from the seabed last night.

They also pulled a ghost net out of the ocean. 

MV Pride is working on retrieving containers in the outer reaches of the salvage site, requiring extensive sailing time in expected worsening conditions.

Onshore, 10 emptied containers have been sent directly for metal scrapping. Processing of 14 containers is underway, including a 46-tonne cargo of nappy absorbent (sodium polyacrylate) retrieved last week.

Nappy absorbent
Processing of a 46-tonne container of nappy absorbent is underway at Port of Newcastle.

 

28 April: Another “lost” container discovered during salvage 

Another missing container off the Hunter Coast is now accounted for after it was discovered during salvage operations yesterday. It brings the total number of containers to be recovered during this operation to 63, with only 13 still unaccounted for.  

Ten containers were lifted from the seabed between Friday night (24 April) and this morning. Two containers proved difficult to separate as their twist locks were seized and had to be cut, causing delays to their salvage.  

On Monday (27 April), MV Pride returned to the port of Newcastle and discharged 24 containers for processing. The ship returned to sea on Monday evening to retrieve the remaining 12 identified containers.  

The containers currently being processed at the onshore waste facility contain a range of materials including plastic jars, car parts, crockery, toilet paper and office chairs.  

The weather for the next few days is favourable however deteriorating weather conditions are expected to set in on Thursday. 

Waste processing of glass jars
Plastic jars are offloaded at Port of Newcastle
Waste processing of car parts
Plastics are among the contents of 24 containers to be sorted and processed

 

24 April: Broken containers and car parts safely salvaged 

Clean-up of auto spare parts littering the seabed is underway along with the retrieval of broken containers off the Hunter Coast. 

Four containers were recovered overnight, containing furniture, plastic jars, car parts and office chairs. One of the containers was empty and crushed immediately for metal scrapping at Port of Newcastle. 

Robotic equipment including a Remote Operated Underwater Vehicle (ROUV) and grab are working to clear the seabed of the pollution.  

Crew aboard MV Pride have retrieved 41 of 62 containers so far and work is underway to prepare the onshore waste processing area for 20-25 containers to be offloaded this weekend. 

Robotics are used to clear car parts and what looks like a vehicle bonnet.
Robotics are used to clear car parts and what looks like a vehicle bonnet. 
container under water
Broken container and furniture will be processed for salvage, recycling and waste onshore. 
23 April: Salvage image gallery launched 

Rolls of carpet, foodstuff, bathroom pods and 46-tonnes of sodium polyacrylate, commonly used as nappy absorbent, are among the contents of four containers retrieved from the seabed off the Hunter Coast overnight. 

In the next few days, crew on the MV Pride will use a robotic grab to retrieve a steel beam and a container in poor condition.  

To date, 37 containers have been retrieved, with 25 yet to be salvaged. 

All retrieved containers offloaded ashore last weekend have been processed and the site cleared for the expected discharge of between 20-25 containers this weekend. 

Cylinders reported yesterday are being investigated to ensure correct disposal is carried out. 

You can view images of some of the salvage operations and findings in our new photo gallery

Sign up for our weekly bulletin at OperationRecovery@amsa.gov.au 

truck and container

22 April: Grab and ROUV to collect loose debris 

Several surveys of recovered container sites have been completed, resulting in the collection of loose debris and a stack of timber from the Hunter Coast seabed.  

Two containers were retrieved overnight, one was heavily damaged and crushed on the deck of MV Pride and safely stored. 

Assorted metal frames and bathroom pods believed to be cargo from the two damaged containers will be retrieved using a grab guided by an ROUV. 

Gas bottles, bikes and glassware are among the contents of the containers offloaded at Port of Newcastle on the weekend, as waste processing continues.  

All empty containers are being processed as scrap metal. 

Gas bottles, glassware and bikes are among the overnight finds from containers opened onshore. 

Cylinders

Glassware

Crushed bikes
21 April: Salvage at halfway mark 

The YM Efficiency container salvage operation has reached halfway with 31 of the 62 containers scheduled for retrieval off the Hunter Coast now recovered. 

Four containers were recovered overnight and compared to the vessel manifest. They’re expected to hold toilet paper, plastic jars, auto spare parts and bathroom pods. 

Broken containers were cut up on the deck of MV Pride and stored for onshore waste processing. 

Onshore, eight offloaded containers have been emptied and are ready for scrap metal loading. 

MV Pride has returned to three sites to verify structural conditions of several containers following poor visibility over the weekend. 

Office chairs have been unloaded and containers are ready for scrap metal processing

Waste processing crew are using heavy equipment to unload bathroom pods

20 April: Salvaged bikes stopped in their tracks 

Office chairs, electronics, tyres, bicycles and bathroom pods are being processed for disposal after MV Pride offloaded 16 containers at Port of Newcastle during the weekend. 

To date, 27 containers have been retrieved from the seabed along the Hunter Coast, including three uplifted on Saturday.  

This week, the MV Pride will continue work to retrieve the remaining 35 identified containers, once visibility improves.  

A two-metre rolling swell has impeded efforts to conduct site surveys due to less than .25 metres bottom visibility. 

Crew have used this time to crush a severely damaged container on the vessel’s deck and store the debris in waste containers for safe disposal ashore. 

You can view footage of one of the containers being emptied

Bikes will be unpacked for waste processing
Bikes will be unpacked for waste processing

 

Processing of LED screens and electronic goods is underway
Processing of LED screens and electronic goods is underway
17 April: Clean-up underway after three containers separated

Crew on the MV Pride worked overnight to raise four containers from the seabed off the Hunter Coast.

Operations now are underway to clear the seabed of debris from a broken container following deployment of a diamond wheel cutting saw to separate a stack of three containers.

Waste processing of nine containers taken ashore on Monday is continuing at Port of Newcastle where a bobcat is being used to clear out debris from the containers.

A shipment of mobile scooters is being processed and batteries are being separated out for safe disposal.

Weather conditions are forecast as favourable and the salvage is expected to continue over the weekend.

Diamond saw cutting containers apart
Diamond saw cutting containers apart
batteries
Scooter batteries
16 April: Smooth sea lift of five stacked containers

The MV Pride has successfully recovered 19 containers lost overboard the YM Efficiency since the salvage operation commenced off the Hunter Coast on 6 April.

This includes a large stack of five containers dismantled and lifted overnight.

The containers were compared against the vessel’s manifest and are believed to hold bicycle and truck parts, cameras and homewares.

The salvage operation is on schedule and based on ROUV surveys to date, the current rate of recovery is estimated at four containers each day.  The long-range weather forecast indicates favourable conditions for the next seven days of operations.

Waste processing of nine containers offloaded at the Port of Newcastle early this week is expected to be completed by tomorrow (17 April). All emptied containers will be sent to scrap for processing.

container lift

 

cardboard

15 April: Successful upload of four damaged containers

Hardwood, tyres, furniture and plastic jars were among the contents of four damaged containers sea lifted onto the vessel MV Pride overnight.

Crew recovered the four broken containers that proved difficult to retrieve from the seabed at site #17, due to their poor condition.

One container was almost empty and held the remnants of its cargo of plastic jars, which were captured and stowed aboard.

MV Pride’s heave compensating crane recorded a 220-tonne load of the full container of hardwood, which dropped to 50 tonnes once the container was drained of seawater.

The vessel has relocated to site #29, to retrieve a stack of five containers in good condition, while waste processing of nine containers continues at Port of Newcastle.

incident recovery map

14 April: waste processing of nine containers underway 

Nine containers from the YM Efficiency salvage operation have been safely offloaded at the Port of Newcastle and waste processing is now underway. 

Seven containers were recovered between Thursday (9 April) and Saturday (11 April).  

The containers housed machinery, scooters, furniture, plastic and utility trucks.  

On Sunday poor weather set in with 30-knot SW winds and 4-metre swell, giving the MV Pride an opportunity to return to port to offload the containers for waste processing and undertake load handling deck modifications, repairs to the steel basket and construction of a landing frame for a spreader. 

The vessel has since returned to sea and crew are working to separate two very damaged containers at site #17.

See our photos below and footage of the first container to be offloaded from MV Pride for waste processing.

The first container is offloaded from the MV Pride at Port of Newcastle on Sunday.
The first container is offloaded from the MV Pride at Port of Newcastle on Sunday.
Utility truck is delivered to Port of Newcastle for waste processing.
Utility truck is delivered to Port of Newcastle for waste processing.

 

Tyres offloaded and ready for processing.
Tyres offloaded and ready for processing.

Waste processing is underway.

8 April 2020: two more containers recovered and two missing containers located. 

During pre-lift surveillance of one of the container sites, an additional two containers were identified for recovery that were previously unaccounted for.  This site was previously believed to contain two containers joined together but with the better cameras aboard the MV Pride’s ROUV, it was discovered there are actually four containers at this site. 

The finding means the number of shipping containers being salvaged as part of Operation Recovery – YM Efficiency, now total 62 and there are only 14 containers yet to be located. 

Two more containers have been recovered since the last update and are now stowed on the deck of MV Pride intact. These containers are believed to contain tyres and paper products.

Vessel movement caused some delays to sea lifts overnight and improvements to handling arrangements are underway to improve the speed and safety of handling the recovery basket.

To date, three containers have been retrieved since Monday 6 April and there are 59 containers still to be recovered. 

Check out our video footage of the remote underwater vessel connecting rigging to the steel recovery basket and lifting a container onto the MV Pride.

Basket with container being loaded onto the ship
Basket with container being loaded onto the ship

 

Basket with container
Basket with container
7 April 2020: first container retrieval

 Retrieval work has begun with the first of 60 shipping containers lost from the container ship YM Efficiency successfully lifted from the seabed off the coast of Newcastle yesterday.

The subsea lift of the first container took place yesterday morning (6 April) at 0900 using a hydraulic crane and rigging, remote underwater vehicles and a specially manufactured steel basket. 

According to the manifest the first container is believed to be carrying furniture products, the container was brought to the surface intact and will not be opened until brought ashore to the waste processing facility. The container was successfully lifted from the ocean bed, transferred into the basket and safely on-board the salvage vessel MV Pride without releasing any further pollution into the environment.  

The MV Pride has begun salvage operations in clear weather with a moderate swell and slight seas, at the site of the main cluster of containers off the Hunter Coast in New South Wales. 

Operation Recovery – YM Efficiency will continue throughout April, weather conditions permitting. 

Subscribe to our mailing list for regular updates on the operation.

incident recovery map
Location of containers

The first container lifted from the sea bed.

First container loaded onto the MV Pride, contains furniture products.
First container loaded onto the MV Pride, contains furniture products.
YM Efficiency ATSB report and salvage update 

If you missed out on attending one of our community information sessions in the Newcastle region last month, you can view and download our presentation on the response to date and overview of the salvage operations.  

We expect the salvage to start next month and to take around four weeks, weather and conditions permitting. 

You may also be interested to read the Australian Transport Safety Bureau’s (ATSB) report on the loss of containers overboard YM Efficiency.  

The report’s findings concluded a structural failure of containers and components of the lashing system, combined with strong weather conditions, led to the loss of 81 containers and damage to another 62 containers. 

You can read the ATSB’s recommended safety actions in the full report

Update—23 March 2020

Preparations are well underway to commence the clean-up operations. The recovery vessel MV Pride is expected to arrive in Newcastle in early April and we will update you once the date is confirmed. The Waste Management Plan for all onshore processing has been reviewed and approved by the NSW Environmental Protection Agency and AVCON Projects has been confirmed as the contractor to manage all onshore waste activities.

We have recently signed a contract with Subsea Pty Ltd to conduct additional searching for the 16 remaining containers not found during the initial search. The search area has been defined based on an analysis of the ship’s track and previous data collected through the subsea scanning.  Work commenced this last week and will continue until the first week of April.

This timing should allow AMSA to negotiate a possible contract extension to remove any newly identified containers during the current project.

Background

On 1 June 2018 the container ship YM Efficiency lost 81 containers overboard into Australian Commonwealth Waters, on the Newcastle-Port Stephens coast. 

Five containers have been removed and there are 16 containers yet to be located.

Contractors removed approximately 1040 tonnes of pollution from around 400 kilometres of shoreline including plastics, furniture, tyres and paper products. 

Leaving the containers in-situ poses an unacceptable environmental risk for the local community and future generations. It also presents a safety risk to local fishers. On 12 December 2019, we signed a contract with Ardent Oceania for the removal and disposal of 60 containers.

The salvage operation will start in March 2020, and the recovery of the containers is expected to be completed within a month, subject to weather conditions.

Debris recovered from the ocean, will be transported to a specially constructed waste reception facility in the Port of Newcastle. 

Here the waste will be classified, stored, transported and disposed of according to NSW Environmental Protection Authority Waste Guidelines.

Risk mitigation will be undertaken to reduce any effects on the marine and coastal environment during the pollution recovery operations. 

Getting the job done

  • Ardent Oceania will be tasked to recover the containers, debris and other pollution from the seabed using an offshore salvage vessel, equipped with specially designed salvage tools.
  • A remotely operated underwater vehicle (ROUV) will be deployed to support recovery operations. The ROUV is equipped to manage crane strops and wires, cut containers to separate them or create water egress holes and to pick up loose debris. 
  • A crane will deposit a large custom fabricated metal basket near the container and the ROUV will assist with attaching the crane to the container and lift it into the basket.  The basket sides are enclosed with small mesh to minimise any spill during lifting and recovery operations.
  • On surfacing, the basket and container will be slowly lifted to drain, then removed by crane for storage on the ship. 
  • There will be no access to containers and the container and contents will be secured until brought ashore and managed according to NSW Environmental Protection Authority Waste Classification Guidelines.
  • If a container can’t be lifted into the basket, the crane will load debris and container components into the basket with a hydraulic grab. Once on board, loose debris will be placed in enclosed bins for removal in port.
  • A small workboat will scour the local sea surface to retrieve any debris which may escape during a lift.
  • The ROUV will assess remaining seabed debris and help guide a crane grab to clear the site. 
  • Finally RUOV will survey the site and provide evidence the site is clear of debris before moving to the next container location.

Onshore containment and disposal

Port of Newcastle will host a temporary area to receive, manage and transport recovered waste. 

A bunding area will be constructed to prevent water pollution from the site entering Port waters. 

The waste management plan and processes will be reviewed and agreed to with NSW EPA to ensure consistency with their regulatory requirements. 

Biosecurity protocols have been addressed with both Australian Border Force and the Department of Agriculture.

Cost Recovery

Since the initial clean-up AMSA has attempted to engage with the Taiwanese owners of the YM Efficiency, Yang Ming, about their ongoing responsibility to remove the remaining containers from the seafloor.

Yang Ming and their insurers Britannia P&I have taken a position that they do not believe that the containers constitute pollution.

The ship’s owners Yang Ming are responsible for retrieving containers and meeting the costs of retrieving containers - the principle being that the polluter pays. Yang Ming’s failure to fulfil their obligations to retrieve the containers has meant that AMSA has stepped in to start the recovery operation. AMSA intends to recover all costs associated with the clean-up from Yang Ming and its insurer Britannia P&I.

Last updated: 29 August 2023