Published on Australian Maritime Safety Authority (https://www.amsa.gov.au)


Report on the 2012 review of the National Plan

AMSA 92 (11/12)
9 September 2012

The 2011/12 Review of Australia’s National Plan to Combat Pollution of the Sea by Oil and Other Hazardous and Noxious Substances (the National Plan) and the National Maritime Emergency Response Arrangements (NMERA) represented a unique and timely opportunity to closely examine Australia’s capacity and ability to respond to maritime casualties and pollution incidents. Not only were both the National Plan and NMERA scheduled for review, but a series of incidents in recent years, namely the Pacific Adventurer and Montara incidents in 2009, were the most comprehensive challenges faced by the National Plan in its 40 year history. The lessons learnt from these incidents covered all aspects of incident response, from weeks of extensive foreshore clean-up close to one of Australia’s largest cities to operating in extremely remote areas of open water.

This Report outlines the outcomes of the Review as agreed by the National Plan Management Committee (NPMC) at its 15th meeting in July 2012. The outcomes draw from the two projects  undertaken during the Review, and comments from more than 90 Australian and international stakeholders that were contacted during the process, including representatives from:

The Review found that despite the many challenges facing the Australian Maritime Safety Authority (AMSA) and the other public and private organisations involved in spill preparedness and response, the National Plan and NMERA have served Australia well over the last ten years. Nevertheless, concerns regarding the current and future management and implementation of the National Plan and NMERA were raised, and areas for improvement identified.

Key outcomes from the Review, as agreed by NPMC , include a number of fundamental changes to the National Plan and NMERA. On the ground, the National Plan and NMERA will be better integrated. This will be assisted by combining them into a single document supported by a single Inter-Governmental Agreement (IGA) that will:

The Det Norske Veritas Final Report: Assessment of the Risk of Pollution from Marine Oil Spills in Australian Ports and Waters (DNV Risk Assessment)1 identified very high maritime risk areas adjacent to and offshore from both Dampier and Townsville. A $25 million program of equipment replacement and refurbishment is well under way and includes replenishment and replacement of the two National Plan equipment stockpiles at these locations. New standards will be developed for equipment storage and maintenance in all nine of the equipment stockpiles. 

To assist in the implementation of competency based training, AMSA will provide resources to assist the States/NT to:

Other outcomes as agreed by NPMC include: 

The National Plan Management Committee believes that the implementation of these changes will ensure Australia’s capability to respond to maritime casualties and pollution incidents will remain effective in the future. NPMC has indicated that the successful implementation of the Review’s outcomes will involve considerable effort by AMSA and all the National Plan/NMERA stakeholders over the next 12-18 months. This will remain a key challenge for all concerned.